The short version
A construction loan pays for the build in stages, called draws, as work gets finished and inspected. You pay interest only on what's been drawn. When the house is done, the loan either converts to a regular mortgage (a one-time-close or construction-to-perm loan) or you pay it off with a separate mortgage (a two-time close).
My strong preference for most owner-occupants is the one-time close. One application, one set of closing costs, and your permanent rate gets set up front or locked before you start. The two-time route has you qualifying twice, and if rates or your income shift mid-build, that second approval isn't guaranteed. I've seen it bite people. Details below, but rates, down payments and terms change, so treat any numbers here as approximate and verify them for your scenario.
How does a construction-to-permanent loan work?
You get approved for the whole project: land (if you're buying it), construction costs, and sometimes a contingency reserve. The lender orders an appraisal based on the finished home, using your plans and specs, not what's standing on the lot today. That 'as-completed' value drives your loan amount.
Then the build starts. The builder finishes a phase, say foundation or framing, an inspector confirms it, and the lender releases that draw. Typically that's five to seven draws over the project. You're paying interest only on the money out the door, so early payments are small and grow as the build progresses.
When the certificate of occupancy is issued, the loan converts to a standard fixed or adjustable mortgage. No new application, no new appraisal in a true one-time close. That's the whole appeal.
- Typical build timeline underwritten: 9 to 12 months, sometimes longer for complex sites
- Interest-only during construction, then a 15-, 20- or 30-year term
- Money flows to the builder in draws, never as a lump sum to you
How much down do I need for a construction loan?
It depends on the program. Conventional construction-to-perm loans generally want somewhere around 10 to 20 percent down, with better pricing at the higher end. FHA one-time close construction loans can go as low as 3.5 percent down for qualified borrowers, and VA construction loans exist too but the lender pool is thin. Jumbo construction is possible, though expect a bigger down payment and tighter reserves.
Here's the good news if you already own your land free and clear: the lot counts as equity. If it's worth $300,000 and the build costs $600,000, you might be putting zero cash in because the land covers the down payment. If you owe something on it, the payoff gets rolled into the new loan and the remaining equity counts. Lender specifics vary, so run your numbers before you assume.
Can I rebuild after a fire with a construction loan?
Yes, and Sonoma County has more experience with this than anywhere in California. If you lost a home in the Tubbs, Kincade or Glass fires and still own the lot, the same construction-to-perm structure applies. Sometimes you already have a paid-off mortgage, sometimes insurance money is part of the picture. Both are workable.
The wrinkle is the paper trail. Lenders want your plans, your permits, your builder's contract and your insurance settlement documented. If you're using insurance proceeds, they can be counted toward your equity or held and disbursed alongside the draws. Underinsurance is the common problem. I'll tell clients straight: if the settlement doesn't cover the build cost, we need to find the gap before you break ground, not at framing.
Also look at defensible space, fire-hardening requirements and what your future homeowners policy will cost. That part feeds directly into your debt-to-income ratio. Read my piece on homeowners insurance in fire zones before you finalize a lot or plan.
What do lenders require from my builder?
More than most buyers expect. The builder has to be licensed in California, carry general liability and workers' comp, and give the lender financials, references and past project history. Many lenders won't approve a builder with fewer than a few years or a handful of completed homes. An owner-builder, meaning you acting as your own contractor, is much harder to finance and some lenders won't touch it at all.
That's the part people underestimate. A great builder with no lender relationship can slow your approval by weeks. If you're interviewing builders now, ask early whether they've worked with construction lenders and whether they'll submit their approval package up front.
And get a fixed-price contract, not cost-plus, when you can. Cost overruns on a cost-plus job come out of your pocket, not the lender's.
Where do these deals go wrong?
Three places, over and over. First, the budget is light. Site work in Sonoma County, think grading, retaining walls, driveways, utility trenching, can run well over a first estimate, especially on hillside lots. Well and septic on a rural parcel adds more. If you're buying land too, see my post on land and lot loans before you make an offer.
Second, permits. Sonoma County planning review can take longer than you'd hope, and your rate lock and loan approval have an expiration date. A delay of a few months is normal. A delay of a year can force a re-underwrite.
Third, change orders. Every upgrade you decide on mid-build either eats the contingency or needs more cash from you. Decide on finishes before you close the loan, not after the framers leave.
None of these is fatal. They're just easier to plan for than to fix.
Is a construction loan better than buying an existing home?
Sometimes. Building gets you exactly the house you want, new systems and warranties, and in some cases a lower all-in cost than a comparable finished home in Santa Rosa or Windsor. But it takes longer, carries more risk and demands more of your time. If you need to move in six months, buy something that's built. If you've got a lot, a plan and a year of runway, building is a serious option, and often worth a conversation before you decide.